BRIEF NOTE ON JNNURM PROJECTS AT A GLANCE


Mission launched by Government of India in December' 2005 with duration of 7 years to ensure planned growth with reforms.

Mission has two sub-mission

(i) UI & G (Urban Infrastructure and Governance) (ii) BSUP (Basic Services for Urban Poor)

PROJECT STATUS U.I.G. B.S.U.P. TOTAL
No. Est. Cost No. Est. Cost No. Est. Cost
Sanctioned by GOI 14 1589.44 7 531.67 21 2121.11
Status of Sanctioned Projects
a) In progress 6 1296.05 2 303.45 8 1599.50
b) Completed 8 293.19 5 228.22 13 521.61
Total 21 2121.11
Amount so far released from GoI Rs. 853.36 Cr
GoAP TotalRs. 353.11 Cr
TotalRs. 1206.47 Cr
Amount spent so far by ULBRs. 526.23 Cr
Expenditure Incurred So farRs. 1732.69 Cr
Value of Work done So farlRs. 1759.70 Cr
Status of JNNURM Projects
Sector Description of Project Status
Water SupplyReplacement of existing Thatipudi Pipeline Completed
Water SupplyProviding pipeline from TSR to Yendada and to Kommadi Junction Completed
Water SupplyAugmentation of Water Supply to Gajuwaka Completed
Water SupplyRefurbishment of Water Supply Distribution in Gajuwaka Completed
Water SupplyAugmentation of Drinking Water Supply to 32 peripheral areas of GVMC 83.50% Completed
Water SupplyRefuribishment of Distribution of Comprehensive Water Supply System in North Eastern Zone in Central Area of GVMC.75.00% Completed
Water SupplyComprehensive Water Supply System in Old City of GVMC.86.50% Completed
Water SupplyImprovement of 24X7 Water Supply in leftout areas of South West sector of GVMCWork started
Storm WaterRegularization of S.L. Canal Completed
Storm WaterRegularization of Yerrigedda Completed
Storm WaterImp. of Storm Water Drains for Zone - VIII of GVMC Gangulagedda & Yerrigedda Branch Canal). Completed
SewerageProviding Sewerage System in old City Completed
SewerageSewerage System in the Central Part of Visakhapatnam90.50% Completed
Urban TransportProviding BRTS in Visakhapatnam in Two Corridors including Flyover80.50% Completed
BSUP - InfrastructureInfrastructure to Sri Nagar Poor Settlement Completed
BSUP - InfrastructureInfrastructure to Yathapalem Poor Settlement Completed
BSUP - InfrastructureInfrastructure to Vadlapudi Poor Settlement Completed
BSUP - InfrastructureInfrastructure to 5 Poor Settlements (Sy.No.179 & Sy.No.27 of Madhurawada, Vambay Colony of Madhurawada, Duvvada & Aganampudi. Completed
BSUP - InfrastructureInfrastructure to 11 Poor Settlements (Pedagantyada, Gangavaram, Bhanojithota, Aganampudi, TGR Nagar, Sebastian Colony, Chakirevukonda, Sivashaktinagar, Rasalamma Colon, etc Completed
HousingProviding Housing & Civic Infrastructure in 22 Poor Settlements (7352 Houses) (Package-I)95% Completed
HousingProviding Housing & Civic Infrastructure in 6 Poor Settlements (7968 Houses) (Package-II)80.50% Completed

JNNURM PROJECTS PROGRESS AT A GLANCE

JNNURM Presentation DOWNLOAD