(Rs. in Crores)
| S.No. | Description of Project | Project Cost | Expd. incurred so far | Value of work done | Remarks |
|---|---|---|---|---|---|
| UI&G | |||||
| 1 | Water Supply Sector:- Replacement of existing Thatipudi Pipeline | 62.28 | 59.79 | 61.17 | Completed. |
| 2 | Providing pipeline from TSR to Yendada and to Kommadi Junction | 23.40 | 23.35 | 23.40 | Completed. |
| 3 | Augmentation of Water Supply to Gajuwaka | 39.76 | 36.35 | 39.50 | Completed. |
| 4 | Refurbishment of Water Supply Distribution in Gajuwaka | 46.00 | 36.28 | 36.57 | Completed. |
| 5 | Augmentation of Drinking Water Supply to 32 peripheral areas of GVMC (Rev.Cost : Rs.256.45Cr.) | 240.74 | 211.93 | 217.89 | 83.5% work completed. Balance work under progress. |
| 6 | Refurbishment of Distribution of Comprehensive Water Supply System in North Eastern Zone in Central Area of GVMC. | 190.18 | 120.02 | 129.17 | 75% completed .Balance work under progress. |
| 7 | Comprehensive Water Supply System in Old City of GVMC. | 47.93 | 38.46 | 38.76 | 86.5% completed. Balance work under progress. |
| 8 | Improvement of 24x7 Water Supply in leftout areas of South West sector of GVMC | 83.48 | 8.69 | - | New work sanctioned. Agreement entered and survey work completed Mobilization advance paid. |
| Sub-Total | 733.77 (749.48) | 534.87 | 546.46 | ||
| 9 | Storm Water Sector:- Regularization of S.L. Canal | 3.39 | 3.35 | 3.35 | Completed. |
| 10 | Regularization of Yerrigedda | 9.21 | 10.84 | 10.84 | Completed. |
| 11 | Imp. of Storm Water Drains for Zone - VIII of GVMC (Gangulagedda & Yerrigedda Branch Canal). | 72.27 | 64.18 | 65.25 | Completed. |
| 12 | Sewerage Sector:- Providing Sewerage System in old City | 37.08 | 37.08 | 37.08 | Completed. |
| 13 | Sewerage System in the Central Part of Visakhapatnam (Rev.Cost : Rs. 264.01 Cr.) | 244.44 | 229.50 | 234.28 | 90.50% Work completed.Balance work under progress. |
| 14 | Urban Transport:- Providing BRTS in Visakhapatnam in Two Corridors including Flyover (Rev.Cost : Rs. 454.00) | 452.93 | 383.07 | 388.40 | Overall 80.50% Completed. (STC-87.10%, PTC-80%, Flyover-92.5% completed. A total of 43 KM of road work taken up. Balance work under progress. |
| UIG (14 Projects) | 1553.09 (1589.44) | 1262.89 | 1285.66 | ||
| 15 | BSUP - JNNURM-Housing: 7352 Houses in 22 Poor Settlements (Package-I) | 90.99 (143.79) | 144.25 | 145.69 | Beneficiaries occupied at Madhurawada, Kommadi, Bakkannapalem, Sebastian Colony, etc. locations . Balance Housing and Infrastructure works are in brisk progress. |
| 16 | 7968 Houses in 6 Poor Settlements (Package-II) | 96.86 (159.66) | 122.80 | 122.80 | |
| 17 | BSUP-Infrastructure: Infrastructure to Sri Nagar Poor Settlement | 2.40 | 2.13 | 2.13 | Completed. |
| 18 | Infrastructure to Yathapalem Poor Settlement | 5.50 | 5.22 | 5.22 | Completed. |
| 19 | Infrastructure to Vadlapudi Poor Settlement | 28.00 | 26.00 | Completed. | |
| 20 | Infrastructure to 5 Poor Settlement | 97.20 | 84.15 | 85.20 | Completed. |
| 21 | Infrastructure to 11 Poor Settlements | 95.12 | 85.87 | 87.00 | Completed.. |
| BSUP (7 Projects) | 416.07 (531.67) | 469.80 | 474.04 | ||
| JNNURM Total (21 Projects) | 1969.16 (2121.81) | 1732.69 | 1759.70 |