JNNURM PROJECTS PROGRESS AT A GLANCE

(Rs. in Crores)

S.No. Description of Project Project Cost Expd. incurred so far Value of work done Remarks
UI&G
1 Water Supply Sector:- Replacement of existing Thatipudi Pipeline 62.28 59.79 61.17 Completed.
2 Providing pipeline from TSR to Yendada and to Kommadi Junction 23.40 23.35 23.40 Completed.
3 Augmentation of Water Supply to Gajuwaka 39.76 36.35 39.50 Completed.
4 Refurbishment of Water Supply Distribution in Gajuwaka 46.00 36.28 36.57 Completed.
5 Augmentation of Drinking Water Supply to 32 peripheral areas of GVMC (Rev.Cost : Rs.256.45Cr.) 240.74 211.93 217.89 83.5% work completed. Balance work under progress.
6 Refurbishment of Distribution of Comprehensive Water Supply System in North Eastern Zone in Central Area of GVMC. 190.18 120.02 129.1775% completed .Balance work under progress.
7 Comprehensive Water Supply System in Old City of GVMC. 47.93 38.46 38.76 86.5% completed. Balance work under progress.
8 Improvement of 24x7 Water Supply in leftout areas of South West sector of GVMC 83.48 8.69 - New work sanctioned. Agreement entered and survey work completed Mobilization advance paid.
Sub-Total 733.77 (749.48) 534.87 546.46
9 Storm Water Sector:- Regularization of S.L. Canal 3.39 3.35 3.35 Completed.
10 Regularization of Yerrigedda 9.21 10.84 10.84 Completed.
11 Imp. of Storm Water Drains for Zone - VIII of GVMC (Gangulagedda & Yerrigedda Branch Canal). 72.27 64.18 65.25 Completed.
12 Sewerage Sector:- Providing Sewerage System in old City 37.08 37.08 37.08 Completed.
13 Sewerage System in the Central Part of Visakhapatnam (Rev.Cost : Rs. 264.01 Cr.) 244.44 229.50 234.28 90.50% Work completed.Balance work under progress.
14 Urban Transport:- Providing BRTS in Visakhapatnam in Two Corridors including Flyover (Rev.Cost : Rs. 454.00) 452.93 383.07 388.40 Overall 80.50% Completed. (STC-87.10%, PTC-80%, Flyover-92.5% completed. A total of 43 KM of road work taken up. Balance work under progress.
UIG (14 Projects) 1553.09 (1589.44) 1262.89 1285.66
15 BSUP - JNNURM-Housing: 7352 Houses in 22 Poor Settlements (Package-I) 90.99 (143.79) 144.25 145.69 Beneficiaries occupied at Madhurawada, Kommadi, Bakkannapalem, Sebastian Colony, etc. locations . Balance Housing and Infrastructure works are in brisk progress.
16 7968 Houses in 6 Poor Settlements (Package-II) 96.86 (159.66) 122.80 122.80
17 BSUP-Infrastructure: Infrastructure to Sri Nagar Poor Settlement 2.40 2.13 2.13 Completed.
18 Infrastructure to Yathapalem Poor Settlement 5.50 5.22 5.22 Completed.
19 Infrastructure to Vadlapudi Poor Settlement 28.00 26.00 Completed.
20 Infrastructure to 5 Poor Settlement 97.20 84.15 85.20 Completed.
21 Infrastructure to 11 Poor Settlements 95.12 85.87 87.00 Completed..
BSUP (7 Projects) 416.07 (531.67) 469.80 474.04
JNNURM Total (21 Projects) 1969.16 (2121.81) 1732.69 1759.70